12 active construction projects • Click phone numbers to call
| Client | Address | Status | Type | Start | Finish | Notes |
|---|---|---|---|---|---|---|
| Frey | 6154 Simpson Avenue | Punch Out | Major Renovation | 11/10/2025 | 05/30/2026 | wallpaper, backsplash, final appliances Friday |
| Frank - Phase 2 | 9939 White Ave | In Progress | Addition | 02/01/2026 | 06/05/2026 | Driveway this week? Garage door install Wednesday |
| Werdel-Bell | 13 Ladue Estates | In Progress | Kitchen | 01/19/2026 | 06/05/2026 | flooring 2nd coat Wednesday - install missing parts Thursday |
| Wilkinson | 5211 Westminster Place | In Progress | Historic | 05/04/2026 | 12/31/2026 | Demo all week, walls and ceilings 3rd floor - waiting on engineer |
| Herr | 9417 Sonora Ave | Schedule Subs | Multiple | 06/01/2026 | 10/30/2026 | PERMITTING. PRE-CON 5/20 @ 10:00. START Week of 6/1 |
| Griffith | 104 Arundel Place | Pre-Con | Multiple | 06/15/2026 | 10/15/2026 | ESTIMATING |
| Client | Address | Status | Type | Start | Finish | Notes |
|---|---|---|---|---|---|---|
| TNB Office | 533 Lafayette, 63119 | In Progress | Other | 01/12/2026 | 08/31/2026 | Reschedule Subs reduced scope. Loan APPROVED. Pending permit |
| Pincus | 905 Providence Ave | Punch Out | Multiple | 01/14/2026 | 05/29/2026 | Punch list items, painters electricians |
| Phillips | 16441 Walnut Rail Road | In Progress | Multiple | 04/20/2026 | 08/31/2026 | Electricians, plumbers and hvac, inspections |
| Humes | 2709 N Geyer Road | In Progress | Bathrooms | 05/04/2026 | 06/30/2026 | plumbers, inspections and drywall delivery |
| Klug | 16305 Wilson Creek Ct | Schedule Subs | Multiple | 06/15/2026 | 11/20/2026 | PERMITTING. PRE-CON 5/29 @ 10:30. START Week of 6/15 |
| Seid | 63 Aberdeen Place | Pre-Con | Multiple | 07/06/2026 | 09/30/2026 | ESTIMATING |